Jewel Bako
Sushi Bar / Restaurant

Design and Built

Address: 239 East 5th Street
Ground Floor / Cellar Total sq. ft.: 650 sq. ft.

Design period: 1-1/2 month (2001 January – February)

Construction period: 2-1/2 month (2001 February – April)

New Construction:

 Design / Construction Management
 Logo, Menu and print outs design  Coordination with all contractors / Shop drawings
 Material coordination
 Schedule control
 New Sub-floor and Bamboo flooring
 Fire-rated walls and ceiling
 New Exsaust / H.V.A.C. system and Duct work
 Sprinkler work
 New Plumbing on ground floor / cellar
 Storefront / Glass work
 Upgrade AMP. / Lighting system
 All custom made Millwork / wood paneling
 Custom made steel work